Construction

The six phases of building a house, and what to check before leaving each one

Two of these six phases cannot be undone once you have left them. Those are the ones to slow down for.

7 min read

  1. 1Approvals

  2. 2Foundation

    !Cannot be fixed later

  3. 3Structure

  4. 4Services

    !Test before walls close

  5. 5Finishing

  6. 6Handover

In short

  • Most families run the largest project of their lives on their contractor's plan rather than their own.
  • The foundation and the services are the two phases you cannot cheaply revisit — inspect both before anything covers them.
  • Tie each payment to a phase closing, not to a date in the calendar.

Building a house is the largest project most families ever run, and most run it without a plan of their own — they rely on the contractor's. That is not dishonesty on anyone's part; it is just that the only written plan on site belongs to the person being paid. Knowing the stages, and what should be true at the end of each, lets you ask better questions and catch problems while they are still cheap.

The phases below are the common shape of a build. The names vary by country and by contract, but the order rarely does, and neither do the two places it hurts most to get wrong.

1. Planning and approvals

Before anything is dug: confirmed ownership and boundaries, a budget with a contingency, finished drawings, the permit, and a signed agreement with your contractor. Starting work before the paperwork is complete is the most common way projects stall later — and the stall always arrives after you have spent money, never before.

Leave this phase with the permit number in writing, not with a reassurance that it is coming.

2. Site preparation and foundation

The site is cleared and levelled, the layout is marked, and the foundation is laid and cured. Have the foundation inspected before the structure goes up — it is the one part of the house you cannot fix afterwards.

If you only insist on one inspection in the whole build, insist on this one.

3. Structure

Walls, columns, slabs, and the roof. This is the phase that looks like progress, and the one where it is easiest to feel reassured by the sight of a building going up. Check the structure against the drawings as it rises — window and door openings in the wrong place are cheap to move now and expensive later.

4. Services: plumbing, electrics, and anything else buried

Pipes, cables, and ducting go in before the walls and floors close over them. Everything in this phase is about to become invisible, which is exactly why it needs testing while you can still see it: pressure-test the plumbing and hold it, check every circuit, and photograph the runs before they are covered.

Those photographs are worth more than they look. In five years, when somebody wants to hang a shelf or chase a leak, they are the only record of what is behind the wall.

5. Finishing

Plaster, flooring, tiling, joinery, paint, fittings. The work is more visible and less risky, but the volume of small decisions peaks here, and so does the number of trades who need to be on site in the right order. This is the phase where a written sequence saves the most arguments.

6. Handover

The snag list, the final clean, the certificates, the warranties, the meter readings, and the final payment. Hold back the final payment until the snag list is genuinely closed — it is the only leverage left, and it stops being leverage the moment it is paid.

The same six phases, as a flow you can run

Here is the whole thing as one flow, with the steps in each phase and what you should have at the end of it. A cart marks something to buy or order; a flag marks a step people commonly forget.

House construction

6 phases · 30 steps

  1. 1

    Planning & approvals

    Lock the budget, the design, and the paperwork before any work starts.

    • Confirm plot ownership and survey boundaries
    • Set total budget with a 10–15% contingency
    • Finalise architect drawings and structural design
    • Get building permit / plan approval · after Finalise architect drawings and structural design
    • Select contractor and sign the agreement

    You'll have: Approved drawings and a signed contract

  2. 2

    Site preparation & foundation

    Clear the site and get the structure's base right.

    • Clear and level the site
    • Arrange temporary water and electricity
    • Mark the layout and excavate
    • Lay footings and foundation
    • Cure foundation and get it inspected · after Lay footings and foundation

    You'll have: Foundation cast and inspected

  3. 3

    Structure

    Columns, beams, slabs, and walls.

    • Build plinth beam and backfill
    • Cast columns and beams
    • Cast floor and roof slabs · after Cast columns and beams
    • Build brick / block walls
    • Structural inspection sign-off

    You'll have: Walls and roof slab standing

  4. 4

    Services rough-in

    Everything that hides inside walls and floors.

    • Electrical conduits and boxes
    • Plumbing and drainage lines
    • Pressure-test plumbing · after Plumbing and drainage lines
    • Waterproof bathrooms, balconies, and roof

    You'll have: Pipes and wiring inside the walls

  5. 5

    Finishing

    Turn the shell into a home.

    • Plastering inside and out
    • Flooring and tiling
    • Doors, windows, and grills
    • Painting
    • Install fixtures, switches, and fittings
    • Kitchen and wardrobes

    You'll have: Rooms painted and fitted out

  6. 6

    Handover

    Check everything, close the accounts, move in.

    • Walk through and write the snag list
    • Fix all snag-list items · after Walk through and write the snag list
    • Get completion / occupancy certificate
    • Permanent utility connections
    • Settle final payments and collect warranties

    You'll have: Keys, certificates, and warranties

Every phase of a house build, in order, with what each one leaves you holding.Open this flow →

What to do with this

Print it, or run it. Either is better than carrying it in your head. If you run it, the useful part is not the ticking — it is that the notes against each phase become the record of the build: who said what, which colour was agreed, when the inspection happened.

Put it into practice

Build your first flow, or start from a ready-made one, in a couple of minutes.

Read next